PROJECT DATA

Construction Site in Munich,
Site management votes for cost-cutter MevaDec

Project: 38 residential units are being built on the site of the historic Kegelhof mill

Owner: Public housing authority, Munich, Germany

Contractor: Zechbau GmbH, Munich brand

MEVA Systems: Slab formwork MevaDec, Circular formwork Radius, Working platform LAB 130, Wall formwork StarTec 

Formwork Engineering: MEVA Formwork Systems, Munich

 
 
1
2
3
4
5
 

Project

Quote: Faster and more Cost-Effective

Site management on “Kegelhof” project in Munich votes for cost-cutter MevaDec

A typical city construction site in Munich where 38 residential units are being built on the site of the historic Kegelhof mill. The old building is being torn down and partly rebuilt.

The building site is cramped, the time schedule very tight. Every square metre of space and every minute of delivery have to be carefully planned. When deciding on the slab forming method, site management followed a simple but effective principle: The largest slab area costing the most in terms of inventory, labour and effort would point to the most suitable method. MevaDec won the contest because it requires the lowest inventory and is fastest in assembly and stripping. Filler areas are reduced to a below 20 cm, reducing costly and time-consuming site-built solutions. Importantly, there is simply no crane time available, so the formwork had to be a true handset system. The subcontractor needed to become familiar with it quickly and work fast with no assembly errors.

Site manager Maximilian Postenrieder: “After only very brief training, the teams achieved very fast assembly times with MevaDec. We cover almost the entire slab with it, except for one large concrete beam in the underground parking lot and the filler areas. The 5 storeys of both buildings all have varying layouts which are quick and cost-effective to form with MevaDec. We use the drop head to strip early and quickly re-use the material on the next pour. This reduces on-site inventory and saves space, this was one of the most important criteria!”

Safety Inspectors give go ahead
Safety is a No. 1 priority. “Safety inspectors are on site every week to check that all safety regulations are being adhered to”, says deputy site manager Georg Klunker. “We use a safety harness to work on top of the formwork, lowering the panels into the beams from the top. This reduces effort, saves time and makes work flow easier to coordinate.”

 
  • MEVA Expertise & References

    MEVA Expertise & References

    Referencen for Projets in Commercial & Residential Construction, Architectural Construction, High-Rise Construction and Civil Engineering Construction

  • Biogen biopharmaceutical production plant in Luterbach near Solothurn, Switzerland

    Biogen biopharmaceutical production plant in Luterbach near Solothurn, Switzerland

    High, Fast, Safe: A state-of-the-art biopharmaceutical production plant is being built for the US biotechnology company Biogen, located on the grounds of a former paper factory in Luter bach near Solothurn, Switzerland.

  • Floating High Over Deep Ground

    Floating High Over Deep Ground

    One of the latest thrills: Float like a bird at a skydiving center, where an artificial airstream will keep you up in the air.

  • Saving 4 Weeks on Schedule

    Saving 4 Weeks on Schedule

    The solution: table forms, 5.40 m long to exactly fit into the openings between the columns. Short filler pieces with rounded edges provided a perfect match to the column layout.